Kiewit/Sundt Joint Venture

The Kiewit/Sundt Joint Venture (KS) is in the beginning stages of design for the Green Build Program, specifically the Landside Improvements of Terminal 2 at the San Diego International Airport. The design effort is led by URS Corporation. The project is targeting a LEED Silver Certification from the United States Green Building Council.

The major elements of construction are comprised of the following: roadway improvements, second level departure roadway with passenger processing facilities (Smart Curb), temporary build out of Gate 19 - to be used as a temporary USO facility, reconfiguration of transit center, reconfiguration of surface parking lot, a new building to house the USO and Parking Management Offices, and Pedestrian bridges to connect the Smart Curb pavilions to Terminal 2.

The project is being developed using a progressive design-build delivery method enabling close collaboration between the Airport Authority and the Joint Venture. One major focus is to maximize opportunity for local contractors and vendors wherever possible and to make this landmark project truly a community effort.

The progressive design-build approach allows construction to start while the specialized design is still underway. Bid packages will be staggered as the design advances, with construction packages bidding into 2011. Initial construction started in the last quarter of 2009 with the build out of Gate 19 providing temporary USO facilities for our troops.

Below are packages scheduled to be posted along with their approximate values:

Asphalt Paving $4,600,000
Dewatering $60,000
Gas Service Lines $1,000,000
Pavement Markings $300,000
Steel Reinforcement $11,900,000
Roadway Signs $2,900,000
Landscaping & Irrigation $3,800,000
Architectural Hardscape $2,250,000
Smart Curb Steel & Misc. Metals $2,100,000
Decorative Railings $190,000
USO/PMO Millwork $35,000
Smart Curb Framing Drywall $520,000
Smart Curb Sheet Metal $2,600,000
Roofing $110,000
Overhead Doors $20,000
USO/PMO Plaster $320,000
USO/PMO Acoustical Ceilings $100,000
USO/PMO Flooring $85,000
USO/PMO Painting $55,000
USO/PMO Signage $20,000
USO/PMO Operable Partitions $30,000
Site Electrical $4,750,000
Building Electrical $4,600,000
Traffic Signals $600,000
Concrete Flatwork $3,060,000
Guardrail $420,000
Concrete Pile $8,100,000
Bridge Post Tensioning $700,000
Site Fencing $430,000
Minor Building Demolition $65,000
Masonry $620,000
USO/PMO Steel & Misc. Metals $790,000
Smart Curb Millwork $660,000
Waterproofing $280,000
USO/PMO Framing & Drywall $640,000
USO/PMO Sheet Metal $270,000
Doors, Frames & Hardware $150,000
USO/PMO Glazing Systems $415,000
Ceramic Tile $80,000
Linear Metal Ceilings $270,000
Smart Curb Painting $260,000
Smart Curb & Site Signage $1,800,000
Specialties $120,000
Flagpoles $30,000
HVAC $1,165,000
Plumbing $615,000

The project team looks forward to the participation of the local subcontractor and supplier community throughout the course of the project. We are committed to maximizing opportunities for the smaller local firms. To meet this goal, we will be packaging work into smaller scopes (where appropriate). In this spirit, major trade contractors are strongly encouraged to provide every opportunity for local, small and disadvantaged firms to participate in their bid. The Green Build Program is a landmark project for San Diego, built for and by the local community!

For questions on Contract 2 Bid Opportunities with Kiewit/Sundt, please contact Mike Sigman at mike.sigman@kiewit.com.

 