The Turner/PCL/Flatiron Joint Venture has begun the process of designing and building
a $460,000,000 expansion of Terminal 2 at the San Diego International Airport.
The scope of work includes construction of a three-story, ten gate expansion of
Terminal 2 consisting of a ticket lobby, airline check in, security screening, baggage
handling, seating areas, concessions and support space. Also included is approximately
1,500,000 sq. ft. of new taxiway and Jet parking. The project is targeting a LEED
Silver Certification from the United States Green Building Council upon completion
in late 2012. The lead designer under the Joint Venture is HNTB with local Architect
Tucker Sadler and Associates providing key support.
The project will be developed using a Progressive Design Build delivery method enabling
close collaboration between the Airport Authority and the Joint Venture working
to the development of a GMP. A major focus is to involve local contractors and vendors
wherever possible to make this landmark project truly a community effort.
The Progressive Design Build Approach allows construction to start even while the
highly specialized design is still in progress. Bid packages for the Terminal and
the Airside will be staggered as the design advances, with Terminal construction
packages bidding through mid 2011. Initial construction work commenced in the Summer
2010.
The Project Team looks forward to the participation of the local subcontractor and
supplier community throughout the course of the project. By packaging the work into
smaller scopes where appropriate, opportunities will be provided for smaller local
firms that might otherwise be excluded from a project of this magnitude. In this
spirit it will be strongly recommended that all major Trade Contractors provide
every opportunity for Small and Disadvantaged firms to participate in this process.
This will be a landmark project for San Diego, built for and by the local community!
To find out more information and to participate in prequalification for bidding
this work,
please register here.
For subcontracting opportunities on the Terminal Development Program, please contact:
Major construction packages under the Turner/PCL/Flatiron Joint Venture are currently
scheduled to bid in the following time frames:
|
Hold Room Seating |
Terminal
|
$1,800,000 |
Q1 2012 |
|
Landscape/Irrigation/Site Furnishings |
Terminal
|
$1,300,000 |
Q1 2012 |
|
Existing Gate Preparation |
Terminal
|
$230,000 |
Q1 2012 |
|
Security Exit Corridor |
Terminal
|
$1,700,000 |
Q2 2012 |
|
Temporary Parking Removal |
Terminal
|
$740,000 |
Q2 2012 |
|
Baggage Handling Systems Fence/Temp. Removal |
Terminal
|
$650,000 |
Q2 2012 |
|
Vendor Buildout & Finishes |
Terminal
|
$520,000 |
Q3 2012 |
|
Special Signage |
|
|
TBD |
|
Bird Deterrent System |
|
|
TBD |
|
Furnishings, FF & E |
|
|
TBD |
Future Scope Opportunity
For future bid opportunities, all information including plans and specifications
will be available at the Airport Authority’s BidsOnline system. Prospective bidders
are required to be registered, and to have successfully completed the
prequalification process.
As the major scopes of work draw closer to starting, there will be more specific
details posted to the website regarding opportunities. Additionally, identified
within each of the scope packages will be supply opportunities.
|